A NEW WAREHOUSE IS BEING BUILT AND THE PRODUCTION FACILITIES ARE BEING EXPANDED IN KIHNIÖ
Project launch in 2023
Construction of a new warehouse began in Kihniö. Earthworks were under way in the autumn, with the aim of completing the hall before winter.
The hall provides 800 m² of new warehouse space. A further 600 m² of the existing warehouse is being converted into heated production space.
December 2023
Construction of the warehouse progressed according to plan. During early winter, the frame was erected and the roof membrane installed, keeping the work well on schedule.
The warehouse was completed in early 2024.
Spring 2025
Once the new Kihniö warehouse was complete, development and conversion work could begin in the old warehouse. Insulation progressed well, followed by finishing the wall and floor surfaces. The conversion was scheduled for completion during the summer, when additional production lines would be installed. This gives us new opportunities and greater production capacity.
Summer 2025
The new facilities converted from the old warehouse entered production use at the beginning of the summer. In addition to the conversion and surface renovation, the lighting was renewed, enabling production work in spacious, bright premises. The next step is to build a connecting passage between the production area and the new warehouse to make forklift traffic easier.